Watch the progress of the Fulford Group Building Expansion
3D Design Concept by APPRO Development, Inc.
3D Design Concept by APPRO Development, Inc.
From Design to Reality by APPRO Development, Inc.
New building with added truck docks, a drive in door and a truck ramp (not shown).
Final - How it was constructed
Start of Construction - November 2014
The start of the exterior walls
Exterior wall prep
Exterior wall prep
Exterior wall prep
Erection of the two-story pre-cast wall panels
Hi/low roof line
Roof installation
Roof installation
Roof installation
Roof installation
Roof installation
Hi/low roof (finished)
The completed roof/ceiling.
Dock door/truck bay construction.
Dock door/truck bays & grading for floors to start
Dock door/truck bays, construction of floors beginning.
Base prep for the "PrimeComposite" floor.
"PrimeComposite" floor poor.
"PrimeComposite" floor poor.
"PrimeComposite" floor poor.
"PrimeComposite" floor poor.
"PrimeComposite" floor.
"PrimeComposite" floor.
"PrimeComposite" floor poor finishing.
"PrimeComposite" floor poor finishing.
The seamless, "PrimeComposite" floor.
Beautiful new, seamless, "PrimeComposite" floors.
The hi/low roof and finished floor.
The finished interior hi/low roof.
Dock door construction.
Ramp construction.
Ramp construction.
Ramp construction.
Ramp construction.
Grid for apron construction.
Concrete pour for apron construction.
Grading for asphalt installation prep.
Asphalt lift.
Grading for asphalt parking lot installation prep.
Asphalt parking lot.
Completed dock doors, apron, asphalt drive and access stairs.
Bathroom construction.
Bathroom insulation.
Bathroom construction nearing completion. Metal stairs, railing and ship's ladder installed.
Drinking fountain and handwash station installed.
Bathroom tile work.
Bathroom stall partitions.
Bathroom finishes.
Storm pond seeding.
Storm pond seeding.
Storm pond seed has become grass.